All projects

Ellis Residence

In progress

Sam & Alex · Fernhill · Sep 7 – Dec 17, 2026

PlannedA preview on the sample project. Changes are saved only in this browser; room progress also shows in the homeowner view.

$77,760
Contract price
incl. approved change orders
$64,515
Invoiced
83% of the contract price
$56,570
Paid
$7,436 deposit not yet applied
$7,945
Owed to you
Invoice 5 due Dec 3
86%
Progress
by room, weighted by price
  • Paid$56,570
  • Owed$7,945
  • Not yet invoiced$13,245

Progress by room

Drag to update
  • Kitchen · Counters in; backsplash, sink, lights and appliances left · Sam & Alex see it85%
    Price $44,520 · invoiced $37,150 · paid $34,600 · $7,370 not yet invoiced
  • Primary Bath · Fixtures in; glass, lights and paint touch-ups left · Sam & Alex see it85%
    Price $22,540 · invoiced $18,265 · paid $15,290 · $4,275 not yet invoiced
  • Permits & Project Management · Sam & Alex see it87%
    Price $7,300 · invoiced $5,700 · paid $5,130 · $1,600 not yet invoiced
  • Change orders · only on your side100%
    Price $3,400 · invoiced $3,400 · paid $1,550

Rooms follow your estimate.

Week of Nov 16

  • Mon 16
    Bath: plumbing fixtures, shower trim and toilet
  • Tue 17
    Bath: tile touch-ups and caulk
  • Wed 18
    Countertops installed
  • Thu 19
    Plumbing: sink drain and disposal; faucet when it arrives · Invoice 5 sent
  • Fri 20
    Meeting: walk the kitchen with Sam and Alex

Next week:

Invoices

  • $7,945
    SentSent Nov 19 · due Dec 3 · $7,945 balance due
  • $10,242
    PaidSent Nov 6 · due Nov 20
    Paid Nov 12
  • $16,013
    PaidSent Oct 23 · due Nov 6
    Paid Oct 29
  • $16,095
    PaidSent Oct 7 · due Oct 21
    Paid Oct 13
  • $14,220
    PaidSent Sep 18 · due Oct 2
    Paid Sep 24

Change orders

Approved $3,400 across 5 change ordersAwaiting Sam & Alex 1 · $1,250
  • Pot filler faucet over the rangeChange order 6 · Nov 17 · labor $550 · material $700$1,250Awaiting client
  • Credit: owners buying the island pendantsChange order 5 · Nov 3 · labor — · material -$900 · on Invoice 4-$900Paid
  • Waterfall edge on the island countertopChange order 4 · Oct 30 · labor $250 · material $1,600 · on Invoice 5$1,850Invoiced
  • Shower tile over the allowanceChange order 3 · Oct 14 · labor $300 · material $700 · on Invoice 4$1,000Paid
  • USB outlets and a second outlet strip on the islandChange order 2 · Sep 29 · labor $380 · material $220 · on Invoice 3$600Paid
  • Replace rotted subfloor under the old dishwasherChange order 1 · Sep 16 · labor $650 · material $200 · on Invoice 2$850Paid

Waiting on Sam & Alex

3 open
  • Change order 6 to approve: Pot filler faucet over the range · $1,250
  • Backsplash tile
  • Shower glass: clear or low-iron?

Activity

  1. You sent Invoice 5 ($7,945)Nov 19
  2. You posted the plan for the week of Nov 16Nov 15
  3. Sam & Alex paid Invoice 4 ($10,242)Nov 12
  4. You posted the plan for the week of Nov 9Nov 8
  5. You sent Invoice 4 ($10,242)Nov 6
  6. Sam & Alex approved Change order 5 (Credit: owners buying the island pendants)Nov 3
  7. You posted the plan for the week of Nov 2Nov 1
  8. Sam & Alex approved Change order 4 (Waterfall edge on the island countertop)Oct 30
  9. Sam & Alex paid Invoice 3 ($16,013)Oct 29
  10. You posted the plan for the week of Oct 26Oct 25