All projects
Ellis Residence
In progressSam & Alex · Fernhill · Sep 7 – Dec 17, 2026
PlannedA preview on the sample project. Changes are saved only in this browser; room progress also shows in the homeowner view.
$77,760
Contract price
incl. approved change orders
$64,515
Invoiced
83% of the contract price
$56,570
Paid
$7,436 deposit not yet applied
$7,945
Owed to you
Invoice 5 due Dec 3
86%
Progress
by room, weighted by price
- Paid$56,570
- Owed$7,945
- Not yet invoiced$13,245
Progress by room
Drag to update
- Kitchen · Counters in; backsplash, sink, lights and appliances left · Sam & Alex see it85%Price $44,520 · invoiced $37,150 · paid $34,600 · $7,370 not yet invoiced
- Primary Bath · Fixtures in; glass, lights and paint touch-ups left · Sam & Alex see it85%Price $22,540 · invoiced $18,265 · paid $15,290 · $4,275 not yet invoiced
- Permits & Project Management · Sam & Alex see it87%Price $7,300 · invoiced $5,700 · paid $5,130 · $1,600 not yet invoiced
- Change orders · only on your side100%Price $3,400 · invoiced $3,400 · paid $1,550
Rooms follow your estimate.
Week of Nov 16
- Mon 16Bath: plumbing fixtures, shower trim and toilet
- Tue 17Bath: tile touch-ups and caulk
- Wed 18Countertops installed
- Thu 19Plumbing: sink drain and disposal; faucet when it arrives · Invoice 5 sent
- Fri 20Meeting: walk the kitchen with Sam and Alex
Next week:
Invoices
- $7,945SentSent Nov 19 · due Dec 3 · $7,945 balance due
- $10,242PaidSent Nov 6 · due Nov 20Paid Nov 12
- $16,013PaidSent Oct 23 · due Nov 6Paid Oct 29
- $16,095PaidSent Oct 7 · due Oct 21Paid Oct 13
- $14,220PaidSent Sep 18 · due Oct 2Paid Sep 24
| Invoice | Sent | Due | Amount | Balance due | Status | Actions |
|---|---|---|---|---|---|---|
| Nov 19 | Dec 3 | $7,945 | $7,945 | Sent | ||
| Nov 6 | Nov 20 | $10,242 | $0 | Paid | Paid Nov 12 | |
| Oct 23 | Nov 6 | $16,013 | $0 | Paid | Paid Oct 29 | |
| Oct 7 | Oct 21 | $16,095 | $0 | Paid | Paid Oct 13 | |
| Sep 18 | Oct 2 | $14,220 | $0 | Paid | Paid Sep 24 |
Change orders
Approved $3,400 across 5 change ordersAwaiting Sam & Alex 1 · $1,250
- Pot filler faucet over the rangeChange order 6 · Nov 17 · labor $550 · material $700$1,250Awaiting client
- Credit: owners buying the island pendantsChange order 5 · Nov 3 · labor — · material -$900 · on Invoice 4-$900Paid
- Waterfall edge on the island countertopChange order 4 · Oct 30 · labor $250 · material $1,600 · on Invoice 5$1,850Invoiced
- Shower tile over the allowanceChange order 3 · Oct 14 · labor $300 · material $700 · on Invoice 4$1,000Paid
- USB outlets and a second outlet strip on the islandChange order 2 · Sep 29 · labor $380 · material $220 · on Invoice 3$600Paid
- Replace rotted subfloor under the old dishwasherChange order 1 · Sep 16 · labor $650 · material $200 · on Invoice 2$850Paid
Waiting on Sam & Alex
3 open
- Change order 6 to approve: Pot filler faucet over the range · $1,250
- Backsplash tile
- Shower glass: clear or low-iron?
Activity
- You sent Invoice 5 ($7,945)Nov 19
- You posted the plan for the week of Nov 16Nov 15
- Sam & Alex paid Invoice 4 ($10,242)Nov 12
- You posted the plan for the week of Nov 9Nov 8
- You sent Invoice 4 ($10,242)Nov 6
- Sam & Alex approved Change order 5 (Credit: owners buying the island pendants)Nov 3
- You posted the plan for the week of Nov 2Nov 1
- Sam & Alex approved Change order 4 (Waterfall edge on the island countertop)Oct 30
- Sam & Alex paid Invoice 3 ($16,013)Oct 29
- You posted the plan for the week of Oct 26Oct 25